PROJECTS

Click on the projects below to expand and see more.

Greenbushes - Blackwood Road Drainage Plan

Project Overview

Undertake detailed design engineering to resolve localised flooding issues along Blackwood Road in Greenbushes

Funding Partner

Talison Lithium

Completion Status

10%

Last Month

·         Developed Engineers brief

·         Consultant engagement

Planned action for next month

·         Stormwater catchment study

Completion

·         End July 2024

Greenbushes - Jephson Street Streetscape Plan

Project Overview

Undertake catchment study followed by concept landscape designs for the Jephson Street median isle.

This will be followed by community consultation to ensure the needs and wishes of the community are met.

Funding Partner

Talison Lithium

Completion Status

10%

Last Month

·         Prepare Landscape Architects & hydrological Engineers brief

Planned action for next month

·         Stormwater catchment study

Completion

·         End August 2024

Greenbushes - Roads Board Toilets

Project Overview

Refurbish the Roads Board toilets whilst making them accessible and compliant.

Funding Partner

Talison Lithium

Completion Status

10%

Last Month

·         Site measure by building designer

 

Planned action for next month

·         Designs produced by building designer ready for construction

 

Completion

·         End August 2024

26IN Greenbushes Youth Precinct Stage 2 - Pump Track

Project Overview

Installation of a new pump track and completion of surrounding landscape

Funding Partner

Talison Lithium

Completion Status

75-100%

Last Month

·         Complete Pump Track construction

·         Complete Landscape design

Planned action for next month

·         Install landscape

Completion

·         End June 2024

Greenbushes - Footpaths

Project Overview

Reconstruction of severely degraded footpaths throughout Greenbushes using several methods to overcome damage by tree roots.

Funding Partner

Talison Lithium

Completion Status

10%

Last Month

·         Review of Concept

·         Commenced Detailed Design RFQ

·         Issue Civil RFQ for asphalt sheeting to some existing paths

Planned action for next month

·         Award Detailed Design for footpaths requiring major interventions

Completion

·         End September 2024

Greenbushes - Roads

Project Overview

Asphalting Woodward at rear of Stinton Gardens,

Asphalting of George St 150m to Tourmaline

Asphalting of Diorite to Galena

Widen Cul-de-sac head on Diorite

Funding Partner

Talison Lithium

Completion Status

0%

Last Month

·         Nil

Planned action for next month

·         Develop roadworks RFQ

Completion

·         End August 2024 pending weather

Greenbushes - Kerbs

Project Overview

Installation of approx. 1km of kerbing within the Greenbushes local roads

Funding Partner

Talison Lithium

Completion Status

0%

Last Month

·         Nil

Planned action for next month

·         Develop roadworks RFQ

Completion

·         End August 2024 pending weather

Greenbushes Hard Courts

Project Overview

Repairs and resurfacing of the Greenbushes Hard Courts

Funding Partner

Talison Lithium

Completion Status

10%

Last Month

·         Developed resurfacing RFQ

·         Issue resurfacing RFQ

Planned action for next month

·         Award resurfacing contract

Completion

·         End July 2024 pending weather

Bridgetown Energy Sustainability

Project Overview

Installation of solar and batteries to the Bridgetown Rec Centre, Library and Civic Centre with energy cost saving going into a sustainability reserve fund.

Funding Partner

Talison Lithium & Department of Sport & Recreation

   

Completion Status

10%

Last Month

·         Completed detailed new energy audit

·         Engaged specialist renewable energy engineer

Planned action for next month

·         Develop construction tenders

Completion

·         December 2024 followed by Western Power approvals

Bridgetown Visitor Centre

Project Overview

Completion of the fit out and landscaping to the Bridgetown Train Station – New Visitor Centre, making it a modern, accessible multi purpose facility.

Funding Partner

Shire and Talison Lithium

 

Completion Status

75%

Last Month

·         Installation of cupboards, desks, audio, electrical, comms, furniture, fencing, bins and planter boxes.

Planned action for next month

·         Installation of connecting pathways, ACROD bays and planting

Completion

·         June 2024

Bridgetown Town Hall including AC & AV

Project Overview

Addition of Air Conditioning, screen and projector to the Town Hall Project, ensuring it will become an all weather and all seasons venue for culture and the arts.

Funding Partners

Shire, Talison Lithium, Lotterywest and WA Recovery

  

Completion Status

75%

Last Month

·         Issue Air Conditioning Tender

·         Award of Tender

·         Install roof access

Planned action for next month

·         Commence internal AC fit out

·         Order major AC components

·         Commence ceiling fit off

Completion

·         November 2024

Greenbushes Railway Station Relocation

Project Overview

Relocation of the Greenbushes Railway Station to the rear of the Greenbushes Discovery Centre. The project includes roof replacement and repairs to the building ready for fit out by the Discovery Centre.

Funding Partners

Shire, Talison Lithium, Lotterywest and WA Recovery

  

Completion Status

75%

Last Month

·         Building Relocation

·         Roof removal

Planned action for next month

·         New roof sheeting installed

·         Flooring repairs

·         Carpentry works

Completion

·         July 2024

Greenbushes Volunteer Bush Fire Station

Project Overview

Construction of a new fit for purpose fire station on Collins Street Greenbushes

Funding Partners

Shire and DFES

 

Completion Status

25%

Last Month

·         Rock breaking and earthworks

·         Sand pad installation

Planned action for next month

·         Plumbing pre-lay

·         Concrete slabs and footings

Completion

·         November 2024